Pakistan has finalised a plan to procure 16 cargoes of liquefied natural gas (LNG) to keep household gas supplies running through the winter, the Petroleum Division announced on Wednesday. The cargoes will cover the four months from November 2026 to February 2027, with the bulk of the supply coming under existing long-term contracts with Qatar and the remaining gaps filled through short-term deals.
The details were shared by Petroleum Minister Ali Pervaiz Malik, Petroleum Secretary Hamed Yaqoob Sheikh and ministry spokesperson Zafar Abbas during an informal interaction with journalists in Islamabad on Wednesday, 18 November. For households that dread the annual winter gas shortage — low pressure, shorter supply hours and cold kitchens — the announcement is the first firm answer to the question of whether this winter will be different.
The Monthly Breakdown — November Secured, January Still Short

According to the ministry’s spokesperson, November’s gas requirements have been fully secured. For December, three of the four LNG cargoes required have already been arranged. January is the tightest month: only one of the six cargoes needed has been secured so far, and the government is working to arrange the remaining five. The briefing did not give a figure for February, the final month of the plan.
The monthly picture matters because winter demand rises sharply. Domestic gas availability is expected to stay at around 1.4 billion cubic feet per day during the winter, while demand in Punjab alone could reach about 1 billion cubic feet per day, according to earlier briefings reported in October. Sui Northern Gas Pipelines expects demand on its network to roughly double, from about 550 million cubic feet a day to 1,100 million, while Sui Southern expects its demand to climb from 300 million to 500 million cubic feet a day.
Where the Gas Will Come From

The plan leans on Pakistan’s long-term LNG contracts with Qatar, which remain the backbone of supply. Shortfalls will be covered through short-term arrangements with Oman, the United States and Azerbaijan’s SOCAR, the state oil company. The minister also announced upcoming high-level visits to Oman to sign agreements formalising cooperation on LPG and LNG.
The 16-cargo figure is tighter than earlier planning estimates reported in October, when one report put the winter requirement at 18 cargoes and an earlier assessment had identified 24. The government has now settled on 16 as the finalised programme. But a plan is not the same as delivered gas: until cargoes are contracted and shipped, the winter supply still depends on deals being closed in time — especially for January.
The winter plan comes against a difficult backdrop for LNG imports. Pakistan’s existing terminals rely on floating storage and regasification units, and the country has no onshore LNG storage. Earlier this month a Pakistan-bound LNG carrier, the Al Mayeda, was struck by unidentified objects near the Strait of Hormuz and forced to turn back — a reminder of how exposed the import chain can be.
Reforms, LPG and the Bigger Winter Picture

Alongside the cargo plan, the Petroleum Division outlined structural reforms for the gas sector. Specialised consultants have been engaged to lead the changes, starting with the separation of the Commercial Gas Sector from the Regulated Gas Sector. A framework for the post-privatisation future of the two gas utilities, Sui Southern and Sui Northern, has been developed after consultations with the World Bank, and discussions with the International Monetary Fund on circular debt and cross-subsidies have been aligned, with full implementation of the transition plan targeted by the end of 2027.
There was also good news on LPG, the fuel millions of households in hilly and remote areas depend on. SSGC LPG Limited has imported a record 15,000 metric tonnes of LPG — the largest single shipment of its kind — which arrived at the Engro Vopak Terminal at Port Qasim. It is the first major import under the government’s revised LPG guidelines, and the government has directed state-owned companies to take the lead in LPG imports ahead of winter to improve availability and ease prices.
For now, the message from the Petroleum Division is reassurance: November is covered, December is nearly there, and the plan for the whole winter is finalised. The test will come in January, when five of the six cargoes are still to be arranged. If those deals close on time, Pakistan’s households could face a winter with gas in the kitchen rather than the usual season of low pressure and cold stoves.
Most Popular
How-ToPTA Tax Calculator 2026: Check Mobile Tax on Any Phone420 views
Pakistan NewsPIA Boeing 787 Lease Deal: What It Means for the Airline396 views
Canada JobsTech Jobs in Canada: Roles, Salaries, and Skills Needed392 views
SportsUEFA Champions League 2026-27: Format, Teams and Schedule389 views
TechnologyPM Shehbaz Sets November Deadline for Alibaba AI and Digitalisation Projects in Pakistan369 views
ShowbizWomen’s Fashion in Pakistan 2026: Trends, Brands and Style Guide366 views